One-time assessment fund at work
3 year plan for – Maintenance and Road system improvements
Back To The Road Commitee Page
Three-Year Road Budgetary Plan.
Second Year -
Above the Concrete Strip, First Curve on
Pinnacle Parkway
PHASE ONE -Road work assessment
First curve above the concrete strip is eroding
away rapidly
PHASE TWO - Solution /Construction
.......
..................
Redirected the road over into the mountain.
This
require excavation into the hillside and
for proper back sloping up hill.. .................................................................................Add Fill and Culvert Extensions
PHASE Three - finished
Well, just when we thought we were finish
we ran into a stumbling block no drainage
water was coming out of the pipe. We had
Joey Beam back up here to dig the pipe back
up. We found the pipe under the road had
rusted out.
Apparently this pipe had been here a very
long time. We had to replace it with a new pipe.