THREE-YEAR ROAD BUDGETARY PLAN.
Introduction
The purpose of this report
To outline the requirements needed to maintain
our road system in a safe and accessible
manner as set forth by the road committee
for the next three years.
Our goal:
For this document to be used to aid the association
in the financial planning for the road system
which will encompass the next three years.
· This report is broken down into three sections,
yearly maintenance, road improvements and
a final annual maintenance and road improvements
cost estimate.
· Yearly maintenance
Periodic gravel and grading are essential
to ensure a proper road surface. Historically
these costs have remained relatively the
same throughout the history of the road.
During the winter months in the past two
years an active snow removal/deicing plan
has been in place to allow accessibility
and ensure safety on the road system during
these weather events. Also within this category
are expenses related to road insurance, Lower
Pinnacle South Association road contribution
and reserve fund contribution.
Road improvements·
Since our road system is now approaching
ten years old problems are developing now
which we feel are due to improper original
road construction, maintenance and natural
erosion. Our area had experienced drought
conditions from approximately 1997 until
2002. Since then we have left the drought
era and now are experiencing a more normal
weather pattern. This is bringing into light
several urgent drainage issues and increased
erosion along our road system. The projects
and drainage maintenance which we feel will
need to be addressed within the next 3 years
are documented within this category. We believe
in taking a proactive approach. Instead of
waiting for a problem to become a major issue
we believe it is in the associations best
interest to remedy the problem before this
happens. There are several reasons for this
including an overall cost savings and more
importantly finding a qualified individual
to perform the work.
From the time the work is ordered until the
time the contractor starts the job can take
weeks even months in this area. In addition
to these projects it is also presumed that
other currently unknown urgent situations
will arise within this period and will need
to be financed solely by our emergency funds.
This category also contains ideas which may
reduce overall maintenance cost and provide
additional safety for our road system.
· Annual maintenance and road improvements
final estimate
This section will summarize the cost of all
road maintenance and improvements listed.
Yearly maintenance-
Gravel and Grading
|
1999-2000 |
2000-2002 |
2001-2002 |
2002-2003 |
2003-2004 |
2004-2005 |
| Gravel |
0 |
2,579.89 |
13,086 |
7,568.86 |
7,830 |
7,700 |
| Grading |
2001.25 |
3,110.00 |
3,010 |
2,380 |
3,205 |
2,700 |
Looking at the graph and table above you
can see since 1999 our expenses for grading
and gravel. We anticipate this trend to continue,
especially since we are seeing more traffic
on our road system as more homes are being
built. The only factor, which may change
this trend, is if a soil stabilization product
is successful. This is discussed under the
road improvements.
$7,700.00 gravel and $2,700.00 grading =$10,400.00
per year
Snow Removal and Deicing
· Ice melt-
This year ice melt was used on two sections
of Pinnacle Parkway which remain icy after
the majority of ice on the rest of the road
had melted. This product worked well and
was very beneficial for the overall safety
of the road.
Ice melt 8 bags per year @ $7.70 per bag
= $61.60 per year
Snowplow-·
This year the association purchased a snowplow
which can be attached to a vehicle. It proved
to be very effective on snow and was used
during at least 3 snow events on the mountain.
Snow fall as deep as 24” was easily removed
from the road with this piece of equipment.
Although no compensation was given to the
operator of the plow we would like to budget
in some moneys to pay for fuel and vehicle
wear and tear in the years to follow. Below
are the estimated hours for snow removal
this year and an hourly rate for compensation.
This number could go up or down depending
on snowfall each year.
Snow Removal -16 hours per year @ $30.00
per hour = $480.00 per year
Ditch Maintenance
· De-silting and debris removal from ditches:
First year:
· 16 hours @ $90.00 per/hour = $1,440.00
Second and Third year
· 8 hours per year at $90.00 per/hour = $1,440.00
($720.00 per year)
Road Improvements
Below are several critical projects we feel
will need to be addressed in the next 3 years
dealing with road maintenance and safety.
Pinnacle Parkway from the locust fence to
the curve before Dave McCaughn’s house:
Starting on the south side of the locust
fence there is an active sinking road shoulder
{see figure 1}. It appears this is due to old stumps being
used for fill along the bank of the road.
These stumps over the years are rotting away
causes instability along the road at this
point. It seems apparent that at anytime
this bank will give way leaving the road
dangerously narrow at this point. Further
up the mountain past the locust fence part
of the shoulder of the road has already given
way leaving a drop off which is currently
flagged {See figure 3}. The locust fence itself is becoming unstable
and needs to be replaced with a more significant
structure. The ditch on the inside of the
road from this point on up to the next curve
is too shallow allowing water to jump the
ditch during heavy rains and cut across Pinnacle
Parkway
{See figure 2}. It is believed that this may be saturating
the shoulder of the road at this point and
has caused the above mentioned shoulder failure.
Further up the road at the curve before Dave
McCaughn’s house where this ditch begins
there are two culverts and two intermittent
streams coming from up the mountain. It has
been observed during heavy rains that one
of these streams overwhelms the culvert and
the excess runs across the road eroding the
inside of the curve at this point {See figure 4}.
Scope of work - Option 1:
Starting with the sinking shoulder the scope
of work includes removing the rotting stumps
and other debris
from below the shoulder and rebuilding the
area with rock and fill, compacting the material
so that it will remain stable. Next the mud
slide above the fence will have large boulders
installed below the road to give an anchoring
point for rock and fill to be placed so that
the shoulder can be rebuilt at this location.
The ditch from this point up to the curve
will be dug deeper using a modified bulldozer
ripper to break threw the solid rock base.
Where the two culverts are located on the
uphill side of the road the two intermittent
streams will be combined and routed to both
culverts so that there flows can be shared
between the two drainage pipes. Also the
inside of the curve will be rebuilt where
erosion has taken place at this point. After
completion of this work a new barrier will
need to be installed to replace the locust
fence and extended further in each direction.
This is described in the guardrails section.
Also all slopes, which have received work,
will need to be seeded with heavy grasses
to aid in stabilization. It is also good
practice to insure sight distances by cutting
back roadside vegetation but low plants and
grasses should be preserved if possible.
Estimated cost: $6,500.00
Note: This price includes using existing
boulders adjacent to the road, which are
not necessary for road stability, and the
use of fill which is blocking the driveway
to Dave Robinson’s cabin located on Pinnacle
Parkway which he has already approved..
Scope of work - Option 2:
Although more expensive a second option may
want to be considered for this section of
road. The road at both the sinking shoulder
and at the slide beyond will be redirected
over into the mountain requiring excavation
into the hillside and proper back sloping
up hill. The shoulders will be seeded with
heavy grasses and sloped to add in stabilization.
The ditch from this point up to the curve
will be dug deeper using a modified bulldozer
ripper to break threw the solid rock base.
Where the two culverts are located on the
uphill side of the road the two intermittent
streams will be combined and routed to both
culverts so that there flows can be -shared
between the two drainage pipes. Also the
inside of the curve will be rebuilt where
erosion has taken place at this point. After
completion of this work a new barrier will
need to be installed to replace the locust
fence and extended further in each direction.
This is described the road improvements section.
Also all slopes, which have received work,
will need to be seeded with heavy grasses
to aid in stabilizing the slopes. It is also
good practice to insure sight distances by
cutting back roadside vegetation but low
plants and grasses should be preserved if
possible.
Pinnacle Parkway above the concrete strip
The inside of the first curve above the concrete
strip is eroding away rapidly
{See figure 5}. There are several reasons for this including
the steepness of the downhill terrain, the
narrowness of the road at this point and
the fact that the culverts do not extend
out far enough out below the road to disperse
the water properly. Recently rip-rap was
installed to slow this process however a
more long term solution needs to be employed.
Scope of work:
Provide culvert extensions to reduce erosion
below the road. Build up the inside of the
curve with rock and fill to bring the road
back up to an acceptable width at this point.
Estimated cost: $3,500.00
Pinnacle Lane:
There is slide near the end of this road,
which was partially removed last year
{See figure 8}. The area was not properly back sloped so
eventually more debri will fall down on the
road. The ditch at this location also was
not re dug after the slide was removed.
Scope of work:
Remove debri and backslope the area to stabilize
the slide. Reseed the area with grass to
slow erosion. Re cut the ditch to allow for
proper road drainage.
Estimated cost: $500.00
Doubleview drive:
The developer of this road never properly
cut ditches or sloped the shoulders of the
road
{See figures 6 & 7}. The spring rains of last year caused severe
damage to this road. Some work was done to
these areas during grading however heavy
equipment will be required to adequately
cut the ditches thru rock and slope the shoulders
to provide a long-term solution to the problem.
Scope of work:
Deepen the ditches on the inside of the turns,
which could not be done by the grader due
to the presence of rock. Also grading the
downhill side of the road above the turns
so that water will run off instead of collecting
on the edge of the road and adding to the
flow of water in the ditch.
Estimated cost: $800.00
Pinnacle Parkway above the Greene’s house
The spillway off of Pinnacle Parkway discharges
into a natural intermittent streambed, which
flows alongside the Green’s residence. During
heavy rains the added rainwater discharge
from Pinnacle Parkway causes flooding along
the edge of the residence. The Green’s have
had a ditch cut to divert the flow and control
it. The ditch is above the lower level of
the home and if overwhelmed or clogged with
sediment would cause flooding and erosion
along the basement wall. This could cause
a liability issue for our association if
damage is done to the residence.
Scope of work:
Divert the flow from Pinnacle Parkway back
to the opposite side of the road using a
headwall and culvert. Line inside of ditch
along Pinnacle Parkway at the curve with
rip-rap to slow the added amount of water
and check erosion. Provide another culvert
back across Pinnacle Parkway past the road
leading down to the Greene’s. This is necessary
since the existing culvert a little ways
further down will not be able to handle the
additional flow.
Additional comments:
The potential of damage to the Green’s residence
can only be partially addressed by fixing
existing road drainage issues. The watershed
from the mountain above the house may still
cause damage even if the road issues are
completely resolved. The location of the
house puts it in jeopardy. This is not an
issue for the association but can be resolved
by the owners if they provide ditching of
increased capacity that insures the non-road
hillside water is contained. Although not
covered in this estimate there has been some
interest in providing a concrete strip at
the steep section of this road to aid in
traction.
Estimated cost: $6,500.00
:
Rip-Rap:
Rip-rap is needed for lining ditches and
slowing down velocity of flow:
2 loads @ $350.00 per/load = $700.00
Placing of rip-rap by machine:
6 hours @ $75.00 per/hour = $450.00
Road Enzymes
SoilTac--Soil Stabilizer is the product we
will be testing in the spring and if all
goes well with the test we will be treating
our more problem areas, to start off we will
be purchasing five gallons, which covers
150 ft for $45.00. This application is for
all-season heavy haul roads. If the product
proves ineffective then this budgeted item
will not be needed. If it proves effective
we will do our most troublesome sections
first, approximately ½ mile, over the next
3 years. If funds are more readily available
then a more aggressive schedule can be made.
SoilTac--Soil Stabilizer is biodegradable,
environmentally safe, polymer based emulsion.
This product is used to stabilize all soils
from dust; erosion and can generate results
similar to the qualities of cement. SoilTac
is designed to work its way down into the
soil creating a thicker protective barrier
with a more rigid and stable road base. We
hope this product will cut cost on gravel
and grading.
2640ft (1/2 mile) of road @ $45.00 per 150
ft. = $792.00 ($264.00 per year)
Guardrails and Concrete Barriers:
In the past few year’s concrete barriers
have been added along some of the more dangerous
portions of our road system. This has worked
well and we will continue to use these however
there are a few areas where the road width
is not sufficient to allow for the use of
concrete barriers. A guardrail system would
be more practical at these locations. Below
are locations requiring safety barriers and
type of barrier system used.
·
Guardrail - Locust fence area
8x8 guardrail system made from pressure treated
wood
Material $15.00 per ft.x 50 ft = $750.00
Labor. $850.00
Total 1,600.00
Pinnacle Parkway between Doubleview Drive
and Tom Pfaffl’s house
Concrete barriers--
Material and labor: 20 barriers @ $100.00
per barrier
Total $2,000.00
Street Signs
Additional street signs are needed in some
locations to aid emergency vehicles and to
help visitors and contractors find their
way in our development.
The following chart indicates the location,
sign nomenclature and cost.
| ,Street Name 6in Reflect Blade |
PRICE |
|
Post |
PRICE |
| Doubleview/ Pinnacle Pkwy intersection, |
$39.00 |
|
No post needed |
0 |
| Pinnacle Pkwy/ REMC intersection |
$39.00 |
......... |
8ft Galv Round |
$22.00 |
| Pinnacle Pkwy/ Tuckback cove intersection |
$39.00 |
|
No post needed |
0 |
| Pinnacle Pkwy and the Greene's |
$39.00 |
|
8ft Galv Round |
$22.00 |
| Total cost |
$156.00 |
|
Total cost |
$44.00 |
Total cost $200.00
Annual maintenance and road improvements
final cost estimate:·
Annual maintenance cost estimate:
1st year
Gravel and Grading
$10,400.00
Deicing
$61.60
Snow Removal
$480.00
Ditch maintenance
$1,440.00
Road supplies
$100.00
Road insurance
$362.00
Pinnacle South road contribution
$4000.00
Reserve Fund
$1000.00
Administrative
$100.00
1st year total
$17,944.60
2nd and 3rd years
Gravel and Grading
$10,400.00
Deicing
$61.60
Snow Removal
$480.00
Ditch maintenance
$720.00
Road supplies
$100.00
Road insurance
$362.00
Pinnacle South road contribution
$4000.00
Administrative
$100.00
Reserve Fund
$1000.00
Per year total
$17,228.60
Road Improvements cost estimate:
Drainage Projects:
Pinnacle Parkway from the locust fence to
the curve before Dave McCaughn’s house
$6500.00
Pinnacle Parkway above the concrete strip
$3500.00
Pinnacle Lane
$500.00
Doubleview Drive
$800.00
Pinnacle Parkway above the Greene’s residence
$6500.00
Road Enzymes Application
$792.00
Guardrails
$1600.00
Concrete Barriers
$2000.00
Street Signs
$200.00
Ditch Rip-Rap
$1,150.00
3 year total
$23,542.00
Per year
$7,847.33 l
|