1. Listed below are my safety related activities during the 3rd Qtr of FY2009.

a) Met with Jim Kiefner -- Queens Gap Construction Manager on 3/26/09 and discussed the following issues:
1. Emergency access by Fire & EMS services using Chalk Creek Road.
2. Emergency egress using Queen Gap roads.
3. Queens Gap Fire Hydrant Access.
4. Chalk Lake Dry Hydrant.
5. Queens Gap's Emergency Access from Pinnacle Parkway.

b) 911 numbers signs. Of the 29 homes built, only 3 do not have the 911 number visible from the road.

c) Conducted review of Pinnacle Parkway for blind-spots. Recommend that a mirror be placed at the "Greene/Maddox " curve.

2. 4th Qtr agenda:
a. Confirm all 911 addresses with local emergency services -- Union Mills, Green River, Shingle Hollow fire stations, & Ruth EMS.
b. Identify fire fighting water sources & their accessibility. Communicate with fire departments.

3. Issues for the Board of Directors:
a. Approval of a safety newsletter.
b. Input FY10 safety goals.



Respectfully Submitted,